  • $20M from NYS + $5.4M from Suffolk County

  • 10,000+ feet of new sewer lines

  • Connecting 120 properties (including 105 Main St. businesses & Kings Wood complex)

  • Supports downtown revitalization

  • Helps local businesses grow

  • Protects the environment

Start Date

Summer 2023 (construction began)


Completion Date

Mid-2025 (final paving and completion estimated)


Location

Main Street (Route 25A): From the entrance to the State Park to Park Avenue

  • Church Street: From Main Street to the Kings Wood complex

  • Meadow Road: Select areas near downtown (exact segments not specified)

Treated Wastewater Disposal Site

  • Recharge Site: A 16.7-acre site at the former Kings Park Psychiatric Center will handle safe disposal of treated wastewater through a groundwater recharge system.

Description

  • $20M from NYS + $5.4M from Suffolk County

  • 10,000+ feet of new sewer lines

  • Connecting 120 properties (including 105 Main St. businesses & Kings Wood complex)

  • Supports downtown revitalization

  • Helps local businesses grow

  • Protects the environment

Start Date

Summer 2023 (construction began)


Completion Date

Mid-2025 (final paving and completion estimated)


Location

Main Street (Route 25A): From the entrance to the State Park to Park Avenue

  • Church Street: From Main Street to the Kings Wood complex

  • Meadow Road: Select areas near downtown (exact segments not specified)

Treated Wastewater Disposal Site

  • Recharge Site: A 16.7-acre site at the former Kings Park Psychiatric Center will handle safe disposal of treated wastewater through a groundwater recharge system.

Description

  • $20M from NYS + $5.4M from Suffolk County

  • 10,000+ feet of new sewer lines

  • Connecting 120 properties (including 105 Main St. businesses & Kings Wood complex)

  • Supports downtown revitalization

  • Helps local businesses grow

  • Protects the environment

Start Date

Summer 2023 (construction began)


Completion Date

Mid-2025 (final paving and completion estimated)


Location

Main Street (Route 25A): From the entrance to the State Park to Park Avenue

  • Church Street: From Main Street to the Kings Wood complex

  • Meadow Road: Select areas near downtown (exact segments not specified)

Treated Wastewater Disposal Site

  • Recharge Site: A 16.7-acre site at the former Kings Park Psychiatric Center will handle safe disposal of treated wastewater through a groundwater recharge system.

Funding Source

Primary Funding: $20 million from New York State's Transformative Investment Program

Additional Funding:

  • $5.4 million from Suffolk County's Capital Program

  • $4 million from NYS Water Quality Improvement Program

  • Potential additional funding from federal infrastructure grants

No direct costs to property owners for initial installation and connection (per Suffolk County's policy for commercial sewer district expansions)

Funding Source

Primary Funding: $20 million from New York State's Transformative Investment Program

Additional Funding:

  • $5.4 million from Suffolk County's Capital Program

  • $4 million from NYS Water Quality Improvement Program

  • Potential additional funding from federal infrastructure grants

No direct costs to property owners for initial installation and connection (per Suffolk County's policy for commercial sewer district expansions)

Funding Source

Primary Funding: $20 million from New York State's Transformative Investment Program

Additional Funding:

  • $5.4 million from Suffolk County's Capital Program

  • $4 million from NYS Water Quality Improvement Program

  • Potential additional funding from federal infrastructure grants

No direct costs to property owners for initial installation and connection (per Suffolk County's policy for commercial sewer district expansions)

Current Status

Nighttime Construction Ongoing
Crews have been working overnight (8:30 PM – 6:00 AM) to finish installing sewer laterals along Route 25A. This work started in late 2024 and continues into spring 2025.

  • Final Road Paving Began in March
    The final paving phase started on March 10, 2025, and is expected to wrap up by mid-May 2025. This includes smoothing roads and repainting traffic lines.

  • Sewer Line Connections
    Sewer connections for eligible properties will begin after paving is complete in May. These will link homes and businesses to the new sewer system.

Next Steps

As of April 2025:

  • Finish Paving and Road Restoration
    Crews are completing paving and restoring all impacted roads with new asphalt and painted traffic lines by mid-May.

  • Sewer Hookups Begin
    After paving is done, eligible properties will begin connecting to the sewer system—helping homes and businesses get off old cesspools.

  • Ongoing Outreach
    Suffolk County Public Works continues to talk with local businesses and property owners to answer questions and help prepare for sewer hook-up.

Project Timeline

Construction Started: Summer 2023

  • Final Paving: March–May 2025

  • Sewer Hookups: Start after May 2025

  • Project Completion: On track for mid-2025

Current Status

Nighttime Construction Ongoing
Crews have been working overnight (8:30 PM – 6:00 AM) to finish installing sewer laterals along Route 25A. This work started in late 2024 and continues into spring 2025.

  • Final Road Paving Began in March
    The final paving phase started on March 10, 2025, and is expected to wrap up by mid-May 2025. This includes smoothing roads and repainting traffic lines.

  • Sewer Line Connections
    Sewer connections for eligible properties will begin after paving is complete in May. These will link homes and businesses to the new sewer system.

Next Steps

As of April 2025:

  • Finish Paving and Road Restoration
    Crews are completing paving and restoring all impacted roads with new asphalt and painted traffic lines by mid-May.

  • Sewer Hookups Begin
    After paving is done, eligible properties will begin connecting to the sewer system—helping homes and businesses get off old cesspools.

  • Ongoing Outreach
    Suffolk County Public Works continues to talk with local businesses and property owners to answer questions and help prepare for sewer hook-up.

Project Timeline

Construction Started: Summer 2023

  • Final Paving: March–May 2025

  • Sewer Hookups: Start after May 2025

  • Project Completion: On track for mid-2025

Current Status

Nighttime Construction Ongoing
Crews have been working overnight (8:30 PM – 6:00 AM) to finish installing sewer laterals along Route 25A. This work started in late 2024 and continues into spring 2025.

  • Final Road Paving Began in March
    The final paving phase started on March 10, 2025, and is expected to wrap up by mid-May 2025. This includes smoothing roads and repainting traffic lines.

  • Sewer Line Connections
    Sewer connections for eligible properties will begin after paving is complete in May. These will link homes and businesses to the new sewer system.

Next Steps

As of April 2025:

  • Finish Paving and Road Restoration
    Crews are completing paving and restoring all impacted roads with new asphalt and painted traffic lines by mid-May.

  • Sewer Hookups Begin
    After paving is done, eligible properties will begin connecting to the sewer system—helping homes and businesses get off old cesspools.

  • Ongoing Outreach
    Suffolk County Public Works continues to talk with local businesses and property owners to answer questions and help prepare for sewer hook-up.

Project Timeline

Construction Started: Summer 2023

  • Final Paving: March–May 2025

  • Sewer Hookups: Start after May 2025

  • Project Completion: On track for mid-2025

Purpose

Economic Development

  • More business opportunities: Restaurants, cafés, and bars can now open or expand without septic limitations.

  • Mixed-use development: Enables apartments above shops and revitalized storefronts.

  • New investment: Previously unusable properties are now viable.

  • Attracts new businesses: Makes vacant/commercial spaces usable again.

Property Value

  • Homes and commercial buildings connected to sewers usually gain value and flexibility.

Environmental Protection

  • Reduces nitrogen pollution and contaminants from old septic systems.

  • Helps protect local groundwater and surface waters (like the Nissequogue River).

  • Supports the Suffolk County Subwatersheds Wastewater Plan.

Public Health & Safety

  • Reduces septic system failures that risk drinking water.

  • Ensures wastewater is treated safely through a regional system.

Flood Protection

  • Sewer system upgrades reduce flooding risks during storms.

Downtown Revitalization

  • A key piece of the Kings Park Downtown Revitalization Initiative (DRI).

  • Creates a more walkable, vibrant Main Street near the LIRR.

  • Supports transit-oriented development (TOD).


Concerns:

Construction Disruption

  • Night work (8:30 PM–6:00 AM) along Main Street and Indian Head Road caused detours and business access issues.

  • Concerns about road restoration quality and disruption to traffic and walkability.

Costs & Long-Term Fees

  • An extra $5.4 million was approved in 2023 due to inflation and materials.

  • Homeowners may pay an estimated $548/year, businesses around $1,507/year.

  • Seniors and fixed-income residents have raised concerns about affordability.

  • Post-construction fees and taxes are still a topic of discussion.

Timeline Concerns

  • Past delays from state and county funding processes have caused frustration.

  • While sewer work is nearing completion (as of Spring 2025), some residents remain skeptical about remaining project timelines.

Overdevelopment Pressure

  • Sewer access makes development easier—raising concerns about overdevelopment and potential changes to Kings Park’s small-town feel.

  • Questions remain about whether sewer lines will expand into nearby residential neighborhoods.

Purpose

Economic Development

  • More business opportunities: Restaurants, cafés, and bars can now open or expand without septic limitations.

  • Mixed-use development: Enables apartments above shops and revitalized storefronts.

  • New investment: Previously unusable properties are now viable.

  • Attracts new businesses: Makes vacant/commercial spaces usable again.

Property Value

  • Homes and commercial buildings connected to sewers usually gain value and flexibility.

Environmental Protection

  • Reduces nitrogen pollution and contaminants from old septic systems.

  • Helps protect local groundwater and surface waters (like the Nissequogue River).

  • Supports the Suffolk County Subwatersheds Wastewater Plan.

Public Health & Safety

  • Reduces septic system failures that risk drinking water.

  • Ensures wastewater is treated safely through a regional system.

Flood Protection

  • Sewer system upgrades reduce flooding risks during storms.

Downtown Revitalization

  • A key piece of the Kings Park Downtown Revitalization Initiative (DRI).

  • Creates a more walkable, vibrant Main Street near the LIRR.

  • Supports transit-oriented development (TOD).


Concerns:

Construction Disruption

  • Night work (8:30 PM–6:00 AM) along Main Street and Indian Head Road caused detours and business access issues.

  • Concerns about road restoration quality and disruption to traffic and walkability.

Costs & Long-Term Fees

  • An extra $5.4 million was approved in 2023 due to inflation and materials.

  • Homeowners may pay an estimated $548/year, businesses around $1,507/year.

  • Seniors and fixed-income residents have raised concerns about affordability.

  • Post-construction fees and taxes are still a topic of discussion.

Timeline Concerns

  • Past delays from state and county funding processes have caused frustration.

  • While sewer work is nearing completion (as of Spring 2025), some residents remain skeptical about remaining project timelines.

Overdevelopment Pressure

  • Sewer access makes development easier—raising concerns about overdevelopment and potential changes to Kings Park’s small-town feel.

  • Questions remain about whether sewer lines will expand into nearby residential neighborhoods.

Purpose

Economic Development

  • More business opportunities: Restaurants, cafés, and bars can now open or expand without septic limitations.

  • Mixed-use development: Enables apartments above shops and revitalized storefronts.

  • New investment: Previously unusable properties are now viable.

  • Attracts new businesses: Makes vacant/commercial spaces usable again.

Property Value

  • Homes and commercial buildings connected to sewers usually gain value and flexibility.

Environmental Protection

  • Reduces nitrogen pollution and contaminants from old septic systems.

  • Helps protect local groundwater and surface waters (like the Nissequogue River).

  • Supports the Suffolk County Subwatersheds Wastewater Plan.

Public Health & Safety

  • Reduces septic system failures that risk drinking water.

  • Ensures wastewater is treated safely through a regional system.

Flood Protection

  • Sewer system upgrades reduce flooding risks during storms.

Downtown Revitalization

  • A key piece of the Kings Park Downtown Revitalization Initiative (DRI).

  • Creates a more walkable, vibrant Main Street near the LIRR.

  • Supports transit-oriented development (TOD).


Concerns:

Construction Disruption

  • Night work (8:30 PM–6:00 AM) along Main Street and Indian Head Road caused detours and business access issues.

  • Concerns about road restoration quality and disruption to traffic and walkability.

Costs & Long-Term Fees

  • An extra $5.4 million was approved in 2023 due to inflation and materials.

  • Homeowners may pay an estimated $548/year, businesses around $1,507/year.

  • Seniors and fixed-income residents have raised concerns about affordability.

  • Post-construction fees and taxes are still a topic of discussion.

Timeline Concerns

  • Past delays from state and county funding processes have caused frustration.

  • While sewer work is nearing completion (as of Spring 2025), some residents remain skeptical about remaining project timelines.

Overdevelopment Pressure

  • Sewer access makes development easier—raising concerns about overdevelopment and potential changes to Kings Park’s small-town feel.

  • Questions remain about whether sewer lines will expand into nearby residential neighborhoods.

Who Does What

Suffolk County Department of Public Works (DPW):
Leads design, construction, and overall project management.

Suffolk County Sewer District:
Will operate and maintain the system after construction.

New York State Agencies:

  • TIP Grant Provider: Funded $20M through the Transformative Investment Program.

  • DEC: Oversees environmental permitting.

  • DOT: Approves work along Route 25A.

Town of Smithtown:
Coordinates with the county and state, handles zoning, beautification, and local communication.

Smithtown Planning Department:
Leads zoning updates and downtown redevelopment tied to the DRI.

Kings Park Chamber of Commerce:
Business liaison, helping merchants with updates and sewer connections.

Kings Park Civic Association:
Shares updates, collects community feedback, and hosts forums.

Federal Government:
Provided funding for stormwater and infrastructure upgrades through congressional support.


Links

Kings Park Downtown Project Website
https://www.kpdowntown.com
Smithtown Sewer Project Update (Town of Smithtown)
https://www.smithtownny.gov/CivicAlerts.aspx?AID=2943
Kings Park Downtown Revitalization Action Plan
https://www.smithtownny.gov/kingsparkplan
LaLota Stormwater Funding Announcement
https://lalota.house.gov/media/press-releases/skpfunding
Newsday Article: Kings Park Sewer Project Funding Boost
https://www.newsday.com/long-island/suffolk/kings-park-sewer-project-boost-vzrp1h43
Suffolk County Department of Public Works
https://www.suffolkcountyny.gov/departments/publicworks
Suffolk County Subwatersheds Wastewater Plan
https://www.suffolkcountyny.gov/swp
Kings Park Chamber of Commerce
https://www.kingsparkli.com
Kings Park Civic Association
https://www.kpcivic.org
Suffolk County Legislature Meeting Archives
https://www.scnylegislature.us/meetings

Who Does What

Suffolk County Department of Public Works (DPW):
Leads design, construction, and overall project management.

Suffolk County Sewer District:
Will operate and maintain the system after construction.

New York State Agencies:

  • TIP Grant Provider: Funded $20M through the Transformative Investment Program.

  • DEC: Oversees environmental permitting.

  • DOT: Approves work along Route 25A.

Town of Smithtown:
Coordinates with the county and state, handles zoning, beautification, and local communication.

Smithtown Planning Department:
Leads zoning updates and downtown redevelopment tied to the DRI.

Kings Park Chamber of Commerce:
Business liaison, helping merchants with updates and sewer connections.

Kings Park Civic Association:
Shares updates, collects community feedback, and hosts forums.

Federal Government:
Provided funding for stormwater and infrastructure upgrades through congressional support.


Links

Kings Park Downtown Project Website
https://www.kpdowntown.com
Smithtown Sewer Project Update (Town of Smithtown)
https://www.smithtownny.gov/CivicAlerts.aspx?AID=2943
Kings Park Downtown Revitalization Action Plan
https://www.smithtownny.gov/kingsparkplan
LaLota Stormwater Funding Announcement
https://lalota.house.gov/media/press-releases/skpfunding
Newsday Article: Kings Park Sewer Project Funding Boost
https://www.newsday.com/long-island/suffolk/kings-park-sewer-project-boost-vzrp1h43
Suffolk County Department of Public Works
https://www.suffolkcountyny.gov/departments/publicworks
Suffolk County Subwatersheds Wastewater Plan
https://www.suffolkcountyny.gov/swp
Kings Park Chamber of Commerce
https://www.kingsparkli.com
Kings Park Civic Association
https://www.kpcivic.org
Suffolk County Legislature Meeting Archives
https://www.scnylegislature.us/meetings

Who Does What

Suffolk County Department of Public Works (DPW):
Leads design, construction, and overall project management.

Suffolk County Sewer District:
Will operate and maintain the system after construction.

New York State Agencies:

  • TIP Grant Provider: Funded $20M through the Transformative Investment Program.

  • DEC: Oversees environmental permitting.

  • DOT: Approves work along Route 25A.

Town of Smithtown:
Coordinates with the county and state, handles zoning, beautification, and local communication.

Smithtown Planning Department:
Leads zoning updates and downtown redevelopment tied to the DRI.

Kings Park Chamber of Commerce:
Business liaison, helping merchants with updates and sewer connections.

Kings Park Civic Association:
Shares updates, collects community feedback, and hosts forums.

Federal Government:
Provided funding for stormwater and infrastructure upgrades through congressional support.


Links

Kings Park Downtown Project Website
https://www.kpdowntown.com
Smithtown Sewer Project Update (Town of Smithtown)
https://www.smithtownny.gov/CivicAlerts.aspx?AID=2943
Kings Park Downtown Revitalization Action Plan
https://www.smithtownny.gov/kingsparkplan
LaLota Stormwater Funding Announcement
https://lalota.house.gov/media/press-releases/skpfunding
Newsday Article: Kings Park Sewer Project Funding Boost
https://www.newsday.com/long-island/suffolk/kings-park-sewer-project-boost-vzrp1h43
Suffolk County Department of Public Works
https://www.suffolkcountyny.gov/departments/publicworks
Suffolk County Subwatersheds Wastewater Plan
https://www.suffolkcountyny.gov/swp
Kings Park Chamber of Commerce
https://www.kingsparkli.com
Kings Park Civic Association
https://www.kpcivic.org
Suffolk County Legislature Meeting Archives
https://www.scnylegislature.us/meetings

Frequently Asked Questions

Why is the sewer project happening?

Downtown Kings Park has never had a public sewer system. Businesses have been stuck with old cesspools, which limits what they can do. This project brings the infrastructure we need to grow, attract new shops and restaurants, and protect our environment.

Will I need to connect to the new sewer system?

If your property is included in the service area, you’ll be contacted with specific instructions. Most downtown commercial properties will need to connect. Residential properties may have the option, depending on location and setup.

Will this cost me anything?

You won’t pay for the sewer lines or hookup—that’s covered by state and county funding. Once connected, you’ll pay a yearly sewer fee:

  • Around $548/year for homes

  • Around $1,507/year for businesses
    Final rates will be confirmed before billing begins.

Where does the wastewater go?

Wastewater will be sent to a Suffolk County treatment plant. A 16.7-acre recharge site at the old Kings Park Psychiatric Center will safely return the clean, treated water back into the ground.

Who can I contact if I have questions?

Reach out to the Suffolk County Sewer Project Team:
📧 kingsparksewers@suffolkcountyny.gov
📞 (631) 393-4994

More from
Kings Park
Map showing streets and landmarks with handwritten notes and a highlighted area in yellow.

Sewer Expansion

Short Desc

Map showing streets and landmarks with handwritten notes and a highlighted area in yellow.

Sewer Expansion

Short Desc

Map showing streets and landmarks with handwritten notes and a highlighted area in yellow.

Sewer Expansion

Short Desc

A scenic view of a calm lake with grassy banks, under a bright blue sky with a few clouds.

Long Beach Road Elevation Project

Short Desc

A scenic view of a calm lake with grassy banks, under a bright blue sky with a few clouds.

Long Beach Road Elevation Project

Short Desc

A scenic view of a calm lake with grassy banks, under a bright blue sky with a few clouds.

Long Beach Road Elevation Project

Short Desc

Aerial view of a town intersection with green trees and buildings under a clear blue sky.

Kings Park Downtown Revitalization Initiative (DRI)

Short Desc

Aerial view of a town intersection with green trees and buildings under a clear blue sky.

Kings Park Downtown Revitalization Initiative (DRI)

Short Desc

Aerial view of a town intersection with green trees and buildings under a clear blue sky.

Kings Park Downtown Revitalization Initiative (DRI)

Short Desc

A modern four-story building with large windows and a white facade, surrounded by greenery and vehicles.

Cornerstone (Tanzi)

Short Desc

A modern four-story building with large windows and a white facade, surrounded by greenery and vehicles.

Cornerstone (Tanzi)

Short Desc

A modern four-story building with large windows and a white facade, surrounded by greenery and vehicles.

Cornerstone (Tanzi)

Short Desc

Aerial view of a large parking lot filled with cars near a building, surrounded by green fields.

Destination Kings Park

Short Desc

Aerial view of a large parking lot filled with cars near a building, surrounded by green fields.

Destination Kings Park

Short Desc

Aerial view of a large parking lot filled with cars near a building, surrounded by green fields.

Destination Kings Park

Short Desc

A row of suburban homes with garages and well-maintained lawns under a clear blue sky.

Country Pointe Estates

Short Desc

A row of suburban homes with garages and well-maintained lawns under a clear blue sky.

Country Pointe Estates

Short Desc

A row of suburban homes with garages and well-maintained lawns under a clear blue sky.

Country Pointe Estates

Short Desc

Copyright 2020-24 - All Right Reserved

Copyright 2020-24 - All Right Reserved

Copyright 2020-24 - All Right Reserved